I’d like to create a special metric that calculates all Unplanned Maintenance activities based on the selected Operating States and downtime stoppages based on a defined timebase for unplanned maintenance. How do I get the various timebases out of the system and the related operating states?
1 Answers
victor Staff answered 10 months ago

Time bases serve as a basis for determining key figures. Unplanned maintenance work is included in the time base MALFUNCTION. There is no separate time base for unplanned maintenance, that is, for the repair of machines. Instead, you have the option of grouping the relevant operating states in an operating state class and accessing them.